News
LCG, May 15, 2025--The Federal Energy Regulatory Commission (FERC) announced today the release of the staff’s 2025 Summer Assessment on the outlook for energy markets and electric reliability during the June to September time frame.
Read more
|
LCG, May 14, 2025--The U.S. Nuclear Regulatory Commission (NRC) accepted Dow's construction permit application to build X-energy Reactor Company, LLC's ("X-energy") first small modular reactor (SMR) plant to power a chemical facility in Seadrift, Texas. Dow's wholly-owned subsidiary, Long Mott Energy LLC, is developing the project to provide Dow's UCC1 Seadrift Operations manufacturing site with safe, reliable, and clean power and industrial steam to replace existing energy and steam assets that are approaching end-of-life. The project is part of a demonstration project supported by the U.S. Department of Energy (DOE) and, if approved, would be the first advanced nuclear facility at an industrial site in the United States.
Read more
|
|
|
Industry News
FERC Approves PJM Proposals to Accelerate New Generation Projects
LCG, February 19, 2025--The Federal Energy Regulatory Commission (FERC) last week approved two PJM proposals to improve the approval process and accelerate the construction of new power generation assets, with the ultimate objective of providing sufficient, reliable electricity supplies to customers.
On December 13, 2024, PJM filed revisions to the Reliability Resource Initiative (RRI) to add provisions enabling a one-time reliability based expansion of the eligibility criteria for Transition Cycle #2 of PJM's existing interconnection queue. The RRI modifications are designed to add up to 50 additional projects to be studied in Transition Cycle #2 to address near-term resource adequacy concerns in PJM.
FERC's findings included stating PJM's proposed RRI revisions are just and reasonable, and that they address the possibility of a resource adequacy shortfall driven by significant load growth, premature generation retirements, and delayed new capacity additions.
FERC's second approval was of PJM's December 20, 2024 filing to revise governing surplus interconnection service and to facilitate the rapid expansion of existing and planned generating facilities. FERC accepted PJM's proposed revisions, effective March 7, 2025, as requested by PJM.
In the second filing, FERC found PJM's revisions are just and reasonable. FERC findings include that the revisions will facilitate the use of existing surplus interconnection capacity by (i) removing certain limitations in the PJM Tariff and (ii) making surplus interconnection capacity available sooner in the interconnection process. The revisions will help address PJM's stated near-term reliability needs and increase the overall efficiency of PJM's interconnection queue.
In PJM's Long-Term Load Forecast Report released in January, the PJM RTO annual summer peak load growth and winter peak load growth over the next 10 years are projected to average 3.1% and 3.8%, respectively. The projected annual net energy average load growth is 4.8%. The PJM RTO winter peak load in 2034/35 is forecast to be 198,175 MW, a 10-year increase of 62,048 MW, which equates to adding more than 6,000 MW per year.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|