EnergyOnline
Services

RSS FEED

EnergyOnline.com rss

News

RWE and Meta Announced New PPA for 200-MW Waterloo Solar Project

LCG, March 18, 2025--RWE and Meta today announced a new power purchase agreement (PPA) for offtake from RWE's 200-MW Waterloo Solar Project, which is located in Bastrop County, Texas. Under the agreement, Meta will purchase 100% of the output from the solar facility, which will support Meta's goal of matching its electricity needs with 100 percent clean energy. The project is scheduled to commence onsite construction in late 2025.

Read more

CPUC Approves SDG&E's Westside Canal Battery Energy Storage Expansion Project

LCG, March 14, 2025--The California Public Utilities Commission (CPUC) approved an expansion of San Diego Gas & Electric's (SDG&E) Westside Canal Battery Energy Storage facility. The expansion project is located in California's Imperial Valley and will add 100 MW of energy storage capacity to the existing 131 MW facility. The new capacity is expected to be fully operational by June 2025. Upon completion, the Westside Canal facility, with a total capacity of 231 MW, will be the largest storage asset in SDG&E's utility-owned battery storage portfolio.

Read more

Industry News

Mississippi Public Service Commission Seeks Settlement Agreement for Southern's Kemper County IGCC Project

LCG, June 23, 2017--The Mississippi Public Service Commission (PSC) unanimously passed a motion on Wednesday instructing counsel to prepare an order pursuing potential solutions regarding the Kemper County Power Generation Facility. The order will be presented to the Commission at its July 6, 2017 meeting.

As part of the order, a new docket number will be opened encouraging a settlement to resolve some or all matters in question. The Commission would like a number of issues to be resolved by Southern Company subsidiary Mississippi Power, the Mississippi Public Utilities Staff and intervening parties. Specifically, the Commission would like the settlement to (i) remove risk from ratepayers for the lignite coal gasifier and related assets, (ii) avoid a rate increase to Mississippi Power Company customers, and (iii) modify the certificate issued to allow only for operation of a natural gas facility at the Kemper Project location.

The announcement issued by the PSC set tight schedule for the settlement process, which "shall be filed with the Commission no later than forty-five days from the effective date of the order." If a settlement is filed, a hearing will be set forty-five days from the date of the filing and a scheduling order entered.

A statement issued by Mississippi Power stated, "The PSC provided several guidelines to consider for the negotiations, including the possibility of the project only operating as a natural gas-fueled combined cycle plant. We expect the process for any negotiations and this new docket will be formally addressed as part of a proposed order the Commission will consider at their July 6 meeting."

The initial certificate was approved by the PSC on June 3, 2010. The 582-MW Kemper County project was designed, in a time of higher natural gas prices and anticipated greenhouse gas emission regulations, as an integrated gasification combined-cycle (IGCC) facility intended to showcase new technologies for gasifying coal, together with carbon capture capabilities to capture at least 65 percent of emissions. Like a traditional combined-cycle facility, the plant combines two combustion turbines with one steam turbine - three engines that turn generators to produce electric power. The project includes an adjacent lignite (a low-rank coal) mine.

The Kemper County project began operating in August 2014 fueled by natural gas, as the coal gasifiers were not ready to be placed into service. The project schedule has included a number of delays, including issues experienced with the ash removal system in one of the gasifiers and recent repairs of tube leaks and associated corrective actions in one of the project's syngas coolers. Project costs have also increased beyond initial expectations. The project costs through April were approximately $5.94 billion.

Copyright © 2025 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service