EnergyOnline
Services

RSS FEED

EnergyOnline.com rss

News

FERC Releases the 2025 Summer Assessment for Energy Markets and Electric Reliability

LCG, May 15, 2025--The Federal Energy Regulatory Commission (FERC) announced today the release of the staff’s 2025 Summer Assessment on the outlook for energy markets and electric reliability during the June to September time frame.

Read more

NRC Accepts Construction Permit Application for Dow's Advanced X-energy SMR Project in Texas

LCG, May 14, 2025--The U.S. Nuclear Regulatory Commission (NRC) accepted Dow's construction permit application to build X-energy Reactor Company, LLC's ("X-energy") first small modular reactor (SMR) plant to power a chemical facility in Seadrift, Texas. Dow's wholly-owned subsidiary, Long Mott Energy LLC, is developing the project to provide Dow's UCC1 Seadrift Operations manufacturing site with safe, reliable, and clean power and industrial steam to replace existing energy and steam assets that are approaching end-of-life. The project is part of a demonstration project supported by the U.S. Department of Energy (DOE) and, if approved, would be the first advanced nuclear facility at an industrial site in the United States.

Read more

Industry News

KCP&L Announces Successful Completion of Testing at New Iatan 2, Coal-fired Unit

LCG, August 27, 2010--Kansas City Power & Light Company (KCP&L) and KCP&L Greater Missouri Operations Company (formerly Aquila) yesterday announced that the new Iatan 2, electric generating facility completed in-service testing. Both companies are subsidiaries of Great Plains Energy Incorporated.

The 850-MW, coal-fired unit, located at the existing Iatan Generating Station just outside of Weston, Missouri, will burn Powder River Basin (PRB) coal.

The new unit was agreed upon as part of KCP&L's Comprehensive Energy Plan that was approved by the Kansas and Missouri Commissions in the summer of 2005. The in-service testing is subject to confirmation by regulatory staff of the two Commissions.

KCP&L is now working towards commercial acceptance with the primary vendors on the project.

The Comprehensive Energy Plan (CEP) evolved through a collaborative process with stakeholders that, in addition to allowing Iatan 2, included mandated environmental upgrades at the Iatan 1, coal-fired, power plant. The installation of the pollution control equipment at Iatan 1 was completed in February 2009. The CEP also includes renewable energy projects, transmission and distribution infrastructure upgrades and customer energy efficiency programs.

Copyright © 2025 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service