|
News
|
LCG, November 19, 2025--Oklo Inc. and Siemens Energy announced today that the parties have signed a binding contract for the design and delivery of the power conversion system for Oklo’s Aurora-INL (Idaho National Laboratory) nuclear small modular reactor (SMR). The agreement authorizes Siemens Energy to begin engineering and design work to expedite procurement of long-lead components and to initiate the manufacturing process for the power conversion system. Oklo’s expertise in advanced fission technology will be combined with Siemens Energy’s extensive industry experience with steam turbine and generator systems, with the ultimate goal of generating carbon-free, reliable electricity.
Read more
|
|
LCG, November 19, 2025--NERC yesterday released its 2025–2026 Winter Reliability Assessment (WRA), which concludes "much of North America is again at an elevated risk of having insufficient energy supplies to meet demand in extreme operating conditions." The WRA does state that resources are adequate for normal winter peak demand, but extended, wide-area cold snaps will be challenging.
Read more
|
|
|
Industry News
AmerenUE Plans New Peaking Facilities
LCG, July 15, 2004--AmerenUE plans to install new, natural gas-fired combustion turbines at its existing Venice Power Plant in Venice, Illinois, just north of St. Louis. The project plan submitted for air permits includes three combustion turbines totaling about of 560 MW. However, the immediate plan is to proceed with only two, 170 MW turbines. Construction on the project is planned to begin in the third quarter of 2004, with commencement of operations targeted for October 2005.The existing Venice Plant has a summer capacity of 73 MW. The plant suffered fire damage in August 2000. Two generators, with a combined capacity of 87 MW, were damaged. The remaining capacity was eventually returned to service and operated until it was retired at the end of 2002. The two new units will basically replace the capacity lost when the units were retired. The two new units, which can go from a cold start to full load in 30 minutes, are planned to provide peaking capacity. These units would be dedicated to serve Missouri customers if the Missouri Public Service Commission approves the transfer of AmerenUE-Illinois customers to AmerenCIPS. Without that approval, the units would serve both AmerenUEs Missouri and Illinois customers. The new generation does not count toward the 700 MW of new, regulated generation capacity the Missouri Public Service Commissions is requiring the utility to add by June 30, 2006 as part of the rate case settlement.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|