|
News
|
LCG, November 2, 2026--Vistra Corp. announced on October 30 that, following receipt of all required regulatory approvals, it has completed the acquisition of Cogentrix Energy from funds managed by Quantum Capital Group. The acquisition consists of 10 natural gas-fired power generation facilities totaling nearly 5,500 MW of capacity. The addition of Cogentrix's facilities to Vistra's existing generation portfolio raises Vistra's U.S. generation portfolio to nearly 50,000 MW.
Read more
|
|
LCG, October 23, 2026--INNIO N.V. yesterday announced a 620 MW follow-on order from a developer and operator of mega-scale data center campuses in the United States. Together with the customer's 1.1 GW order announced previously in July, the new order brings cumulative orders from the customer to approximately 1.72 GW this year.
Read more
|
|
|
Industry News
PSC Approves Plan to Construct Two Nuclear Units in South Carolina
LCG, February 12, 2009--The Public Service Commission (PSC) of South Carolina yesterday voted unanimously to approve the application of South Carolina Electric & Gas Company (SCE&G) to construct two additional nuclear reactors at the V.C. Summer Nuclear Station in South Carolina. The first unit is scheduled to commence operations in 2016, with operations of the second unit following in 2019.
The nuclear expansion project is a joint project between SCE&G, the principal subsidiary of SCANA Corp., and state-operated Santee Cooper. SCE&G will hold a 55 percent share, with Santee Cooper holding the remaining 45 percent. SCE&G will operate the two new, 1,117-MW units.
SCE&G and Santee Cooper jointly own the existing 966-MW V.C. Summer plant, and SCE&G is the plant operator. Commercial operations of the existing facility began in January 1984.
The PSC allowed SCE&G to start implementing a rate increase to cover some of the costs to finance the project, given SCE&G shows that the project is on schedule and that expenditures are within limits set in the Commission?s order. The estimated project cost to build both units, excluding the cost to finance and the cost for transmission upgrades, is $9.8 billion.
In May 2008, Santee Cooper and SCE&G announced a contractual agreement with Westinghouse Electric Company, LLC, and Stone & Webster, a subsidiary of The Shaw Group Inc., for the design and construction of the two units.
Approval from the Nuclear Regulatory Commission (NRC) is necessary before construction can begin, and that decision is not expected until late 2011 or early 2012. Santee Cooper and SCE&G submitted an application with the NRC in March 2008 for a combined construction and operating license (COL).
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|