Natura Resources Announces Agreement with NGL Energy Partners to Develop 100-MW SMRs with Large-Scale Produced Water Treatment in the Permian Basin

LCG, February 4, 2026--Natura Resources LLC (Natura), a developer of advanced molten-salt nuclear reactors, announced yesterday that it has signed an agreement with NGL Water Solutions Permian LLC, a subsidiary of NGL Energy Partners LP (NGL), to pursue opportunities to combine Natura's advanced nuclear reactor technology with thermal desalination for power production and oil and gas produced water treatment. NGL transports, treats, recycles and disposes of more than 3 million barrels per day of produced and flowback water generated from crude oil and natural gas production in the Permian Basin.

Read more

OPG Completes Darlington Nuclear Station Refurbishment Project Under Budget and Ahead of Schedule

LCG, February 2, 2026--Ontario Power Generation (OPG) announced today that construction on the four-unit Darlington Refurbishment project is now complete. Station staff are completing final testing, and the last unit is expected to return to service in the coming weeks. OPG stated that the overall project is currently four months ahead of schedule and $150 million under budget.

Read more

Industry News

EPA Reaches Settlement on Four Corners Power Plant

LCG, June 26, 2015-The Environmental Protection Agency (EPA) and the U.S. Department of Justice (DOJ) yesterday announced a federal Clean Air Act settlement with several Arizona and New Mexico-based utility companies to install emission control equipment at the Four Corners Power Plant located on the Navajo Nation near Shiprock, New Mexico.

The settlement requires an estimated $160 million in upgrades to the plant's sulfur dioxide (SO2) and nitrogen oxide (NOx) pollution controls. The settlement also requires $6.7 million to be spent on three health and environmental mitigation projects for tribal members and payment of a $1.5 million civil penalty. The public will have 30 days to comment on the settlement, which will become final with a judge's signature. A federal court must approve the settlement.

Arizona Public Service Company (APS) is the operator and primary owner of the Four Corners Plant. El Paso Electric Company, Public Service Company of New Mexico, Salt River Project Agricultural Improvement and Power District and Tucson Electric Power Company are current co-owners of the plant and Southern California Edison Company is a former co-owner of the plant. The settlement resolves claims that the companies violated the New Source Review (NSR) provisions of the federal Clean Air Act by modifying the Four Corners Power Plant without obtaining required permits or installing and operating the best available air pollution control technology.

The settlement with the APS, the majority owner and primary operator of the power plant, comes without any admission of wrongdoing from APS but levees a $1.5 million civil penalty against APS to be paid within 30 days. The APS vice president of environmental and chief sustainability officer, stated, "The settlement gives us certainty with the plant in regards to the continuing operations (there).Our goal all along has been to provide certainty for the power plant, and this is one more action that we took towards that." The assistant administrator for EPA's Office of Enforcement and Compliance Assurance stated, "All power plants should be using the latest air pollution control technology. The law requires companies to protect clean air, and those living nearby - like Navajo communities - expect it. In addition to installing pollution controls, Arizona Public Service will also take the responsible steps to protect the health of those living near the Four Corners plant, which is one of the largest sources of harmful pollution in the country. The pollution controls for NOx required by the settlement improve the Selective Catalytic Reduction (SCR) controls for the Four Corners Power Plant finalized by EPA in 2012 under the Clean Air Act's regional haze program. The current controls for SO2 will be upgraded to increase their efficiency. The new controls are estimated to reduce SO2 emissions by approximately 4,653 tons per year and NOx emissions by approximately 887 tons per year. The settlement also requires $6.7 million of mitigation funds to be spent on three types of projects, including cleaner heating systems, weatherization and a Health Care trust fund. Southern California Edison will spend approximately $3.2 million on a project to replace or retrofit local residents' inefficient, higher-polluting wood-burning or coal-burning appliances with cleaner-burning, more energy-efficient heating systems. APS and the other current co-owners will spend approximately $1.5 million for weatherization projects for local homes to reduce energy use.
Copyright © 2026 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service