LCG, April 15, 2025--Matrix Renewables announced today the successful commissioning of the Pleasant Valley Solar 1 power generation facility in Ada County, Idaho. The 200-MWac solar facility includes a Power Purchase Agreement (PPA) that was secured through negotiation with Meta and Idaho Power. Matrix Renewables states the facility is the largest operational solar facility in Idaho Power's system. Sundt Renewables, the Engineering, Procurement, and Construction (EPC) services provider, completed construction of the project on March 2nd.
Read more
|
LCG, April 9, 2025--Duke Energy announced yesterday its submission of a subsequent license renewal (SLR) application to the U.S. Nuclear Regulatory Commission (NRC) for the Robinson Nuclear Plant, a 759-MW nuclear unit located near Hartsville, South Carolina. The application requests extending the plant's operations for an additional 20 years.
Read more
|
|
|
Industry News
Hearings Begin for Duke's New Coal-fired Units at Cliffside
LCG, January 18, 2007--The North Carolina Utilities Commission yesterday began a three-day hearing regarding Duke Energy Corp.'s plans to construct two coal-fired units at the Cliffside Steam Station. The hearing resulted from Duke's notifying the Commission that its cost estimate for the two, 800-MW units had increased from $2 billion to $3 billion.
In testimony provided yesterday, Duke witnesses further explained that the $3 billion cost excluded finance costs and that the total cost would be even higher.
The issues to be addressed by the Commission at the hearing are the accuracy of project cost estimate and whether the proposed project is the most economically feasible alternative. Duke anticipates a Commission decision by March. The first unit is scheduled to commence operations in 2011.
Duke originally filed its application with the Commission in May 2005 for a "Certificate of Public Convenience and Necessity" (CPCN) to expand and upgrade the Cliffside Steam Station, located in Rutherford and Cleveland counties, North Carolina.
In October 2006, Duke filed the revised, $3 billion estimate with the Commission on a confidential basis. In November 2006, the $3 billion cost estimate was released in response to pressure from opponents that were aware of Duke's filing a confidential cost update with the North Carolina Utilities Commission. The cost increase was driven by new, firm price quotes for major components of the planned facility.
The Commission had planned to rule on the CPCN for the new coal units by the end of 2006. With the roughly fifty percent increase in the estimated cost, the Commission scheduled the current hearing.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|